CPCCBC4004A - Identify and Produce Estimated Costs for Building and Construction Projects - Engineering Assignment Help

Download Solution Order New Solution
Assignment Task:

Task:

Instructions for this assessment

This is a skill-based assessment and will be assessing you on your ability to demonstrate skills required in the unit.

This assessment is in five parts. The first part is broken into several sub- tasks. For each of these sub-tasks, there is a checklist of statements to show what an assessor will look for in your submitted work. Complete each sub-task, then before you move on to the next one, carefully review your work by reading through the checklist, to make sure you have met all the requirements.

1. Practical Tasks
 Task 1 – Joists for first floor addition
 Task 2 – External wall cladding for first floor addition
 Task 3 – Floor covering for the first-floor addition
 Task 4 – Internal Lining for the first-floor addition
 Task 5 – Painting the for first floor addition
 Task 6 – Plant and Equipment Requirements
 Task 7 – Waste Management
 Task 8 – Apply overheads and margin
2. Role Play – Conduct a Meeting
3. Additional Questions
4. Assessment Feedback.

 

Part 1: Practical Tasks
Background

To support the role of the builder in being able to produce construction industry documentation, student save access to a professional intranet that provides a simulated building company, RB Holdings. RB Holdings functions as a simulated workplace environment where project-based assessments can be undertaken using industry standard documentation, plans, activities, responsibilities and procedures. The RB Holdings business structure allows simulation of work environments such as, but not limited to, design offices, site offices and construction sites.  RB Holdings provides students with relevant documentation that is to industry standard that allows students to experience a professional simulation of a construction office environment.

 

Scenario:
Mr and Mrs Brown have recently met with a Building Design consultant to initiate the design and costing stage for an alteration and addition to their existing house at 1 Lake Road Toronto NSW. You are employed by RB Holdings who have been engaged by their clients, Mr and Mrs Brown, to provide preliminary estimations of products identified by the designer, as a lead up to finalising their project budget.
Development approval is pending from Lake Macquarie City Council, and a set of working plans and specifications, has been drafted for the client. These will need further amendments dependant on the development approval requirements, and the outcomes of your work in this assessment.

 

Task 1.1 – Calculate quantities of floor joists for first floor additions
Considering the Mr and Mrs Brown’s Alterations and Additions – V4004-619.pdf (CPCCBC4004A_AE_Sk_2of4_SR2), you are required to calculate the quantities required for the floor joists for the first-floor additions. The quantities are to be expressed in an accepted industry format.

Task 1.2
Using the following price guide calculate the total cost of the timber:
 HJ300 ‘HyJoist’ at $25.00 per metre.

Task 1.3
You are required to conduct research and access the ‘Fair Work Building and Construction General on Site Award’ and calculate the cost of two Level 3 Carpenters on site for 8 hrs.

 

Task 2: External Wall cladding for first floor addition
Task 2.1 – Calculate quantities of external wall cladding
Using the Mr and Mrs Brown’s Alterations and Additions – V4004-619.pdf (CPCCBC4004A_AE_Sk_2of4_SR2), you are required to calculate the quantities required for the specified external weatherboards the first-floor addition. The quantities are to be expressed in an accepted industry format.

Task 2.2
You are required to research and source a suitable ’Scyon’ cladding product size and price from a reputable building supplier. You are required to calculate and apply the price to find the correct number of boards.

 

Task 3: Floor covering for the first-floor addition
Task 3.1 – Calculate floor covering quantities
Using the Mr and Mrs Brown’s Alterations and Additions – V4004-619.pdf (CPCCBC4004A_AE_Sk_2of4_SR2), you are required to calculate the quantities required for the carpet floor coverings for the first-floor addition, and the games room with the following specifications:
 First Floor carpet - allow 5% waste
 Games Room flooring - allow 2.5% waste.

Task 3.2 – Calculate floor covering costs
Using the following price guide, you are required to calculate the total cost of floor coverings: High Quality nylon/wool blend @ $115.00 per m 2
Laminate floating floor @ $58.00 per m 2 .

Task 3.3
You are required to calculate the labour time on site for the carpet and timber floor layers based on the advice from the suppliers.
 2 x carpet layers able to lay 3m 2 per hour. This includes time to transport, placement and clean-up
 3 x timber floor layers (may be the carpet layers doing this job) able to lay 4.5m 2 per hour. This includes time to transport, placement and clean-up.

 

Task 4: Internal Lining for the first-floor addition
Task 4.1 – Calculate quantities for internal wall and ceiling linings
Using the Mr and Mrs Brown’s Alterations and Additions – V4004-619.pdf (CPCCBC4004A_AE_Sk_2of4_SR2), you are required to calculate the quantities required for the internal wall and ceiling linings for the first-floor addition, with the following specifications:
 Wall linings 10mm standard Plasterboard
 Ceiling linings 10mm Ceiling specific plaster board
Use the surrounding standard room wall height at the stair void, and do not calculate the stair void below the floor level.

Task 4.2
You are to source a suitable product type and price from a reputable supplier and apply square metre price to the calculated quantities for each product.

Task 4.3
You have made enquiries and have been advised by the plastering contractors that they require the following consumables:
 16Kg of Base Coat product per 100m 2 of plaster lining
 10Kg of Topcoat per 100m2 of plaster lining.
 5 Rolls of paper tape for the job.
You are required to calculate the quantities and source prices from a reputable supplier for the consumable items listed above, for a total consumable

 

Task 5: Painting the first-floor addition
Task 5.1 – Calculate quantities of paint.
Using the Mr and Mrs Brown’s Alterations and Additions – V4004-619.pdf (CPCCBC4004A_AE_Sk_2of4_SR2), you should calculate the quantities of paint required for the internalwalls and ceilings for the first-floor addition, with the following specifications:
 1 x Sealer coat in m 2
 2 x Topcoats in m 2
 Assume a single colour for topcoat
 Do not calculate quantities for skirtings or architraves
 Do not calculate ensuite bathroom.
You are required to research the square metre coverage of paint per litre, to convert the calculated square metres into the required number of 10 litre cans and 4 litre cans.

Task 5.2
You are to source a suitable paint brand and price from a reputable supplier and apply the price to the calculated quantities.
You are required to provide details of your supplier sources

 

Task 6: Plant and Equipment requirements
Task 6.1 – Calculate temporary fencing
You are required to research the Work Health Safety requirements to find information about how to restrict access to a construction site in accordance with Local Authority Approval requirements and statutory WHS Legislation.

Task 6.2
Using the information derived from Task 6.1 above, you are required to identify the plant and equipment that is required to safeguard the site.

Task 6.3
You are to obtain base rate (not negotiated) prices from a reputable hire company based on a per week hire rate for the identified plant and equipment in the previous Task 6.2 above.
You are required to provide details of your supplier sources.

 

This CPCCBC4004A : Engineering Assignment has been solved by our Engineering Experts at My Uni Papers. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.